Work-to-complete list
A work-to-complete list is a list compiled by a contractor and issued to each subcontractor and their crews at, or near, completion. It is a list of the remaining items and any defective work that subcontractors required to complete before leaving the site.
The work-to-complete list, enables the contractor to formalise remaining work and ensure that subcontractors properly complete their contractual requirements before final payment is made and they move on to the next job. It can prove difficult to get subcontractors to return to a project once they have left.
The work-to-complete list is similar to the ‘snagging list’ or ‘punch list’, which is a list of faults identified by the appropriate certifying authority (typically the architect, contract administrator, or employer’s agent) which must be rectified before a certificate of practical completion can be issued.
Many contractors will wait for the the snagging list to be prepared before issuing their work-to-complete list. However, the earlier the subcontractors receive the list of remaining items, the sooner the problems are likely to be resolved.
The list should be clear, and very specific so there is no ambiguity about what needs to be done and where.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.